Removes what fouls
The gel membrane (approx. 10 nm size exclusion) holds back particles, colloids and bacteria, then regenerates with a backwash and fresh gel. Dissolved salts pass straight through, by design.
Technology · Reverse osmosis pre-treatment
Purus removes what fouls. UV inactivates what grows. Reverse osmosis removes what is dissolved. Put together, each barrier does the job it does best, and your RO membranes see a far lighter fouling load.
A 96-second walk through the train: why RO membranes foul, what Purus and UV take out ahead of them, what is left for the RO, and the evidence behind it.
Reverse osmosis is the stage that removes dissolved salts, but particles, colloids and microbes build a layer on the membrane surface. Feed pressure and energy rise, cleaning becomes more frequent, and membranes are replaced early. In a study of full-scale plants in the Netherlands, fouling accounted for around a quarter of RO operating cost, mostly through early membrane replacement and extra energy.
The gel membrane (approx. 10 nm size exclusion) holds back particles, colloids and bacteria, then regenerates with a backwash and fresh gel. Dissolved salts pass straight through, by design.
UV inactivates bacteria and viruses that pass the gel, especially as the gel loads between renewals. It adds no chemicals, so disinfection puts no chlorine on chlorine-sensitive polyamide membranes. Already-chlorinated town or recycled water keeps its carbon or bisulphite stage.
With the fouling load taken out upstream, the membranes work on what only they can remove: dissolved salts, metals and small organics. The aim is a slower pressure rise, with cleaning and replacement spaced further apart.
Far less particle, colloid and microbial load reaching the most expensive stage in the plant.
UV disinfects without adding chlorine, so disinfection adds nothing for chlorine-sensitive membranes to cope with.
Purus cleans itself with a backwash and fresh gel, instead of disposable cartridges.
Installs ahead of the plant you already run, sized by the vessel as a skid, container or multi-vessel train.
Where it fits: cooling-tower and data-centre make-up water, recycled water, bore and surface water, and process water ahead of RO. Antiscalant and other RO chemistry for dissolved scale-formers is still set by the RO design; Purus and UV address particles, colloids and microbes.
CS Energy, Kogan Creek dam. Multi-pass Purus trial, samples analysed by ALS Laboratories.
Up to about 10% at Kogan Creek, largely from reduced fouling of downstream RO membranes.
Published laboratory tests of the hydrate gel, on fresh gel under test conditions.
Silt density index, membrane pressure drop and cleaning interval, before any commitment.
Trial results are site-specific. Sources: Jafari et al., “Cost of fouling in full-scale reverse osmosis and nanofiltration installations in the Netherlands”, Desalination 500 (2021) 114865; Malekizadeh & Schenk, “High flux water purification using aluminium hydroxide hydrate gels”, Scientific Reports 7, 17437 (2017); CS Energy case study. More on the UV stage: UV disinfection.
Blue Quest can supply the whole train: Purus, UV and a packaged reverse osmosis stage matched to the Purus flow, run from one controller. Or keep the RO you already have and add Purus and UV in front of it.
| Purus model | Water to the RO | RO product water* |
|---|---|---|
| Purus 20.1 | ~1.5 m³/h | ~1 m³/h |
| Purus 50.2 | ~5.5 m³/h | ~3 m³/h |
| Purus 100.5 | ~8.5 m³/h | ~5 m³/h |
| Purus 100.20 | ~8.5 m³/h | ~5 m³/h |
Stainless-steel RO skid sized to the Purus flow, with a 5 µm guard cartridge and clean-in-place connections.
The RO starts, stops and alarms with Purus and UV, from the Purus controller.
Control panel checked, upgraded where needed and certified to Australian standards by a licensed electrician before installation, with pumps and membranes chosen for local parts and service.
Town and recycled water usually carry chlorine. Where they do, a carbon or bisulphite stage stays ahead of the RO membranes.
*Planning selection only, at 50–75% recovery depending on your water, confirmed by Blue Quest engineering. The standard packaged design suits feed water up to about 1,200 mg/L dissolved solids, such as town, recycled and most make-up water. Higher-salinity water, such as cooling-tower blowdown or brackish bores, is designed individually. Supplied for industrial and process water; drinking-water projects are assessed against Australian requirements case by case. On hard water, softening can stand ahead of the RO.
Every RO site starts with a pilot on its own water, measuring silt density index, membrane pressure drop and cleaning interval. Tell us about your plant, or the plant you need, and we will scope it.